Han-to-Wei Water Diversion Project: QinlingTunnel
The Qinling Tunnel crossing section has a total length of 81.779 km, a design flow rate of 70 m³/s, and an average annual water conveyance volume of 1.5 billion m³. The average hydraulic gradient of the tunnel is 1/2500. Construction was carried out using the drill-and-blast method plus two TBMs with a construction period of 6.5 years. On July 1, 2018, without any precursors, a delayed rockburst occurred within the 180° arch range of the heading at stake K39+393~K39+402.1 (face stake K39+402.1). It formed the largest rockburst cavity since construction, with a cavity depth reaching 10 m. The completed supporting systems including steel arches, anchor mesh and shotcrete within stake K39+379.6~K39+393 suffered severe damage. Meanwhile, the arch erection gantry was instantly destroyed. This rockburst was classified as an extremely intense delayed rockburst.
Hangzhou Tuqiang Company adopted a three-boom rock drilling jumbo for drilling with high-pressure water hole cleaning simultaneously. A Φ45 drill bit (forming hole Φ47 after slight wear) was used. The hole wall was smooth without protruding rocks or hole shrinkage, with only a small amount of rock cuttings, achieving good hole formation. The hole depth ranges from 4.9 m to 5.1 m. The anchor head is fitted onto one end of the anchor rod and screwed until the end closely abuts the U-shaped retaining plate of the anchor head. The anchor head enters the hole and aligns with the borehole axis, then the anchor rod is smoothly inserted, leaving 20 cm of the rod exposed. Pull the rod to expand the split-set anchor head. Install the backing plate, ball washer and nut in sequence, and adjust the angle between the ball washer and backing plate to prevent the rod from being subjected to shear force during prestress trial tensioning. When prestress measurement (or prestress application via jack) is required, place the load cell (or jack) between the ball washer and nut.
For the on-site pull-out test of the anchor bolt, one end of the jack bears against the ball washer while the other end is fixed with a single-hole anchorage. The on-site tension gauge showed 112.54 kN. Tensioning was not continued due to jack capacity limits and site requirements, though the load could be increased further if needed. This indicates that the split-set anchor head inside the borehole engages well with the rock stratum and provides high anchoring force. Piston pumps were adopted for grouting according to site conditions. Limited by the grouting capacity of the piston pump, the grout was mixed with a relatively high water-cement ratio. A Baroid mud balance measured the density at approximately 1800 kg/m³ (water-cement ratio about 0.5). Grout return was satisfactory, demonstrating unobstructed grout passages inside the borehole. After replacing grouting equipment and refining construction details, grout with the required water-cement ratio (0.35~0.4) can be injected. The rockburst hazard was successfully resolved.
Back to list